Construction Update

 
 

JULY 22ND

Level 2 Concrete slab pour is underway, whilst formwork on level 3 has been set-out in the north east portion.

 
Market Lane_Hickory construction.jpg

JULY 12TH

Basement level structure is complete.

Concrete pours have commenced on Level 1 and suspended decks are up and ready for reinforcements to be installed.

IMG_4540.JPG

MARCH 21ST

Excavation is complete.

Ground floor slab is being poured.

Building core is being formed.

Unknown-12.jpeg

JANUARY 19TH

The crane has been erected.

Excavators have been busy digging to a depth of approx. 23 metres and removing approx. 25,000m3 of dirt.

80 foundation piles have been installed.